Bid schedule vs schedule of values

Updated · BuildGets Team

A bid schedule is the owner's list of bid items, with quantities and units, that you price to win the job. A schedule of values (SOV) is the contractor's breakdown of the contract sum, prepared after award, used to bill progress payments. One comes before the contract, the other after it.

Side by side

Bid scheduleSchedule of values
PurposeCompare bids and set unit pricesBill progress payments
Prepared byOwner or engineerContractor, approved by owner or architect
WhenBefore bid day, in the bid documentsAfter award, before the first pay application
ContentsItem numbers, descriptions, units, quantities, blank pricesLine items and their scheduled values, adding up to the contract sum
Typical formBid form inside the bid packageAIA G703 continuation sheet or the owner's pay form

How they connect on unit-price work

On water, sewer and paving jobs paid by unit price, the bid items usually carry straight into the contract as the payment items. Each pay application measures the quantity installed for each item and multiplies it by the bid unit price. That is why the item numbers, units and quantities on your bid schedule matter long after bid day.

Where the mistakes happen

The bid schedule is transferred at least twice: from the owner's PDF into your estimate, and from your estimate into the payment items. Each transfer can drop an item or change a unit. Converting the bid form once, with every item checked, and reusing that list for both steps removes most of that risk. BuildGets BID does the first transfer and marks each item as verified or to review.

Questions

Is a bid schedule the same as a schedule of values?

No. The bid schedule is the owner's list of items you price to win the job; the schedule of values is the contractor's breakdown of the contract sum used to bill progress payments after award.

Who prepares each one?

The owner or engineer prepares the bid schedule. The contractor prepares the schedule of values, and the owner or architect approves it.

On a unit-price job, do I still need a schedule of values?

Usually the bid items themselves become the payment items, measured by installed quantities. Some owners still ask for a schedule of values for lump-sum items.